Building History
Construction
December, 1995 Purchased land from Bonnie Fitzpatrick
March, 1996 Facilities Analysis Team (FAT) Formed
September, 1996 1st Parish-wide Survey Conducted
April, 1997 2nd Parish-wide Survey Conducted
November, 1997 Proposed Master Plan to Diocesan Building & Property Commission
- FAT Disbanded; Work Accomplished
- Program Issues Forwarded to Pastoral Council
- Follow-on Master Plan Development - Building & Property Committee
December, 1997 Formal Diocesan Response Received - Expressed Reservations
- Not Appealing as Presented
- Building Intensive
December, 1998 Follow-up Presentation to Diocesan Building & Property Commission
- Concurred with Diocesan Reservations
- Request Approval & Guidance on Reworking Master Plan
Dec, 1998 - June 1999 Revised Parish Master Plan and Presented to Pastoral Council
June, 1999 - June, 2000 Master Plan Review by parish groups, additional revisions, Presentation and Approval by Diocesan Biuilding & Property Commission
Nov, 2000 - Apr 2001 Prepared and Submitted Site Development Plan to City of Colorado Springs
May - July, 2001 Conducted "With Grateful Hearts…" Capital Campaign
October, 2001 Revised Site Development Plan Approval
June - December, 2001 Solicited Architect Interest & Conducted Selection Process, Selected Architects
December, 2002 Schematic Design Approval from Diocese
April - July 2003 Solicited & Selected General Contractor for Pre-Construction Services
July 2003 Ceremonial Ground Breaking
August 2003 Detail Design Approval from Diocese of Colorado Springs
December 2003 Construction Documents & Supporting Financial Proforma Approval from Diocese of Colorado Springs Approval to Proceed with Construction
March 2004 Construction Begins
December 2004 Construction Complete
December 18, 2004 DEDICATION
 